Cardinia
reservoir.
Cardinia Reservoir was made in the 1960's and was finished in 1973.
I interviewed Craig Reaburn (who works at the
school as a I.T Technician)and who also used to be a student at Emerald Primary
School. He was a part of the construction of Cardinia reservoir. He drove a
bulldozer and cleared out the trees. All the houses on the area where the
reservoir was to be built were sold and destroyed. The roads were closed and moved.
Craig was sixteen years old when he was working on the job. It took
three years to complete and bought many people to Emerald.
Paragraph written by John
|
|
| This is bird's eye view of Cardinia reservoir. | This is a cross section of Cardinia reservoir.All the materials were all found on the site. drawn by Aaron |
| These diagrams show all the info of the Cardinia reservoir. As shown
below. Area of water shed(ha): 2813(1). Type of dam: Rolled earthfill and rockfill embankment. Top water level (Aust height datum): 167.06. Maximum height of dam from river bed to crest: 86 metres. Crest length of dam: 1542(2) metres. Area of water surface at top water level (ha): 1,295. Total available capacity (in megalitres):287,000. Date of completion:1973. |
|
|
| This is a pipe that runs from the Silvan reservoir to Cardinia Reservoir. | This is a sign for the Cardinia Reservoir park. |
|
|
| This is the quarry where they got the rocks for the walls of the reservoir. | This is a photo of a kangaroo taken at Cardinia reservoir. |
| THIS PAGE WAS MADE BY:Aaron and John |